Oswestry Commercial Solar Farm 1.1MW Installation

Category:

Commercial

Date:

July & December 2023

Location:

Oswestry

Duration:

3 Weeks for Phase 1 & 2

The Project

This commercial solar PV project involved the installation of eleven three-phase Solis inverters, ranging from 50kW to 110kW, delivered across two phases.

Oswestry Commercial Solar Farm 1.1MW Installation

Phase 1 – Installing Inverter Mounting Framework using Unistrut

The first phase was completed in July 2023, with our team installing the inverter mounting framework using Unistrut, before connecting and terminating the DC strings into each inverter.

Phase 2 - Works Completed

We returned for the second phase in December 2023 to complete the AC works, including the installation, pulling and termination of the SWA cabling.

MidlandPlus installed metering and connected into a DNO-supplied transformer

Winter conditions brought additional challenges, with cold temperatures and flooding within the cable trenches making the cable installation particularly demanding. Despite the conditions, our team worked through the challenges to successfully complete the installation and deliver a high-quality commercial solar system.