This commercial solar PV project involved the installation of eleven three-phase Solis inverters, ranging from 50kW to 110kW, delivered across two phases.
The first phase was completed in July 2023, with our team installing the inverter mounting framework using Unistrut, before connecting and terminating the DC strings into each inverter.
We returned for the second phase in December 2023 to complete the AC works, including the installation, pulling and termination of the SWA cabling.
MidlandPlus installed metering and connected into a DNO-supplied transformer
Winter conditions brought additional challenges, with cold temperatures and flooding within the cable trenches making the cable installation particularly demanding. Despite the conditions, our team worked through the challenges to successfully complete the installation and deliver a high-quality commercial solar system.